Design-Build for Expediting Project Schedules
Single Point of Responsibility
Design-build provides the owner with a single point of responsibility from project inception, through permitting, design, construction, and start-up/commissioning. Within a very short time frame, a team of design and construction professionals begins collaborating to meet the owner's needs, with communications funnelled through a dedicated project manager. By establishing a single point of responsibility, and a collaborative team of engineer and contractor, the design-build approach drastically reduces the potential for conflicts and claims that can occur on fast-tracked projects. Methods of controlling the designer-builder's cost include lump sum pricing prior to selection, where applicable; or alternately, open-book cost reimbursable approaches when scope uncertainties or need for scope flexibility exists.
Early Establishment of Budget and Schedule
When faced with regulatory deadlines, owners often need to quickly determine the project budget to secure the proper funding, and then carefully plan project cash flow. One of the benefits of the design-build approach is the early establishment of the project budget and schedule. Because the contractor is engaged early in the design process, the budget and schedule are developed before the final design is complete and the owner has reliable cost information much earlier than with traditional design-bid-build projects. Since a detailed project schedule is also developed early, the owner and design-builder can work together to establish the project cash flow and account for any special concerns or limitations. The team can also take it a step further by using advanced project scheduling to account for risks and uncertainties that can hinder the project deadline.
When schedules are tight and the pressure is on, choosing a design-build approach for project completion can make all the difference.
Pre-purchasing and Early Release Packages
During development of the project schedule, the design-build team determines the critical path and identifies long - lead equipment-items that typically take several months to ship - and/or construction packages that have the greatest impact on timely completion of the project. The collaborative nature of a design-build approach enables the contractor to work closely with the engineering team to prepare pre-purchase packages and procure long-lead equipment early in the design process. Using this method, the long-lead equipment is fabricated concurrently with completion of the final design, thereby fast-tracking the overall project schedule.
Early construction activities, such as site civil work and concrete, can also be procured prior to completion of final design by preparing early-release packages. By using early-release packages, the contractor can mobilise earlier and can ensure that when long-lead equipment is shipped to the site, the items can be installed without delay. Because of this ability to quickly advance a project to "shovel ready" status, design-build delivery can provide an advantage for projects receiving public funding.
In contrast to a typical relay-style approach, where one organization handles the design and then passes execution to another group, design-build facilitates interaction and collaboration among field experts right from day one. Specialists in their fields are motivated by the same goals, and are brought in wherever and whenever they are needed in the process.
Be Informed
Design-build can provide owners with a great way to fast-track a project. When executed properly, the result is not only an expedited project, but one that minimises the need for change orders, provides better final work products, and significantly reduces the potential for multi-party disputes.
Choosing the best design-build approach for project completion can make all the difference.